Norwegian company established in 1919 – turnover 900 million NOK – offices in 10 countries

Products
Søk etter innhold

Norwegian Air

Project: New aircraft hangar for 787 Dreamliner
Where: OSL Gardermoen Airport
Client: Norwegian Air Shuttle AS
About project: Steel building of 14000 sqm. (hangar and office space)
Contract: Sales contract NS8407

 

The hangar building has a span of 99 meters, and is 112 meters long. In addition there is an administration- and storage building of more than 3000 sqm. The project ‘s total budget was 250 million NOK.